ComponentOne GanttView for WinForms
Working with GanttView / Task Elements / Task Predecessor
In This Topic
    Task Predecessor
    In This Topic

    GanttView allows you to define task dependencies such as task predecessors and task successors. A task predecessor’s start or finish date determines the start or finish date of its successor task. When you assign a predecessor task in GanttView, the project automatically creates an arrow that points to the following task. If the predecessor type is not specified, the finish-to-start dependency is created by default.

    Additionally you can also specify the lag time if there is an expected delay for something that must happen between two linked tasks by using the Lag property of Predecessor class. For example, this is useful when you are expecting the delivery of materials. Here, you can specify the lag time in days, which is the default unit for lag time.

    You can use the Predecessors and Successors properties of the Task class to add a task predecessor and successor respectively. You can also specify the type of predecessor to be added by using the PredecessorType property of Predecessor class, which takes the PredecessorType enumeration as an input to set the predecessor type to one of the following values:

    Task Image Link Type Description Example
    Displays Finish-to-start task image. Finish-to-start(FS) This dependency is created by default when you link two tasks in C1GanttView. The order in which you select the tasks treats the first as the predecessor, and the second as the successor. The work of task (B) can only start after all the work for task (A) is finished. For example, if you have two tasks, "Dig hole" and "Plant tree," the "Plant tree" task cannot begin until the "Dig hole" task is completed.
    Displays Start-to-start task image. Start-to-start(SS) The dependent task can start at any time after the task that it depends on begins. This dependency is used when two tasks can overlap or be parallel. When you overlap the tasks, it will help reduce the total work time. For example, if Task A takes 7 days and Task B takes 10 days, then the overall time of the two tasks is only 10 days. The SS type does not require that both tasks begin at the same time. For example, if you have two tasks, “Planning phase” and “writing phase”, the “writing phase” task cannot begin until the “planning phase” begins.
    Displays Finish-to-finish task image. Finish-to-finish (FF) The finish date of task (A) determines the finish date of task (B). This dependency is used when two tasks can overlap or be parallel. When you overlap the tasks it will help reduce the total work time. For example if Task A takes 7 days and Task B takes 10 days, then the overall time of the two tasks is only 10 days. For example, if you have two tasks, “set up inner tent” and “snap together poles”, the “snap together poles” (Task B) cannot be completed until the “set up inner tent” (Task A) is completed.
    Displays Start-to-finish task image. Start-to-finish(SF) The start date of Task (A) determines the finish date of the Task (B). This type of dependency usually occurs less frequently. For example, the book shelves for your construction project are built off-site. Two of the tasks in your project are “Wood delivery” and “Assemble book shelves”. The “assemble bookshelves” task cannot be completed until the “wood delivery” task begins.

    Use the below code to add a task predecessor programmatically.

    C#
    Copy Code
    //Add a predecessor
    Predecessor p = new Predecessor();
    p.PredecessorTask = task1;
    Task1.Predecessors.Add(p);