    I am trying out GanttView control and require to set the following scenario.

    The working days start on Tuesday first week. Then work continusouslly for 10 days and have 4 days off (that will be second week Fri, Sat, Sun, Mon is off).

    And then repeat the same.

    Is there a way to set this programatically to show the bars in the grantt for these non-working days.

    Also is there a way to disable some of the commands on the gantt toolbar and add new?

  • Posted 31 May 2020, 11:41 pm EST

    Hi,

    1. Regarding how to define first working day of week to Tuesday.

      Please set the FirstDayOfWeek property to DayofWeek.Tuesday

    2. Regarding how to work continuously for 10 days and then give have 4 days off.

      I am investigating onto this requirement [ID: 438817] and will get back to soon with some information/solution.

    3. Regarding a way to disable some of the commands on the gantt toolbar and add new?

      For this, you can modify the built-in template that is shipped with control and installed at C:\Program Files (x86)\ComponentOne\WPF Edition\C1WPFGanttView.4.5.2\XAML location.

    With regards,

    Ruchir

  • Posted 3 June 2020, 8:38 am EST

    Hello,

    Developer has confirmed that unfortunately, it is possible to implement this only by adding a custom calendar but that will not be reflected on chart as bars.

    So, I am sorry to say your requirement is not possible to implement using C1Ganttview.

    Regards,

    Ruchir